The CQA Consultant is an independent party not affiliated with the contractors, subcontractors, suppliers or manufacturers. The CQA Consultant may be the Design Engineer. The CQA Consultant has the overall responsibility for managing, coordinating and implementing the CQA activities and confirming that the contractor’s construction quality control activities are performed in accordance with the CQA Plan, construction drawings and technical specifications. The critical activities related to the construction, manufacture and installation water pipes, water pumps and
+
The CQA Consultant is an independent party not affiliated with the contractors, subcontractors, suppliers or manufacturers. The CQA Consultant may be the Design Engineer. The CQA Consultant has the overall responsibility for managing, coordinating and implementing the CQA activities and confirming that the contractor’s construction quality control activities are performed in accordance with the CQA Plan, construction drawings and technical specifications. The critical activities related to the construction, manufacture and installation water pipes, water pumps and  
  
 
</div>
 
</div>
 
Previous Page: [[DCOM_Volume_III_Appendix_4]] <<  >> Next Page: [[DCOM_Volume_III_Appendix_6]]
 
Previous Page: [[DCOM_Volume_III_Appendix_4]] <<  >> Next Page: [[DCOM_Volume_III_Appendix_6]]

Revision as of 15:17, 21 July 2022

1 INTRODUCTION

The purpose of this Construction Quality Assurance (CQA) Plan is to detail the testing methods and quality assurance procedures for required Water supply and sanitation projects. The Project includes: • (Narrate the Summarized details of the Project)

2 DEFINITIONS

For the purpose of the CQA Plan, the following terms are defined below: Construction Quality Assurance (CQA) – A planned system of activities that provide assurance that materials or construction activities are undertaken and installed as specified in the drawings and specifications Construction Quality Control (CQC) – The process of measuring and controlling the characteristics of the item/product in order to meet the manufacturers or project specifications. •(Give definition of other terms and materials used)

3 ROLES OF THE PARTICIPANTS

The participants and/or parties that have been identified as key personnel in the delivery of this project include, but are not necessarily limited to (Give the Positions of all key personnel in the project). The roles and responsibilities of the participants and/or parties are detailed below. For example
Project Manager>br> During the Construction, the Project Manager acting on behalf of the Employer, will serve as a single point of contact for the Design Engineer, Contractor and CQA Consultant.

Design Engineer
The design engineering services for the XXXL will be provided by XXXL Consultants. The Design Engineer shall review and approve any proposed changes during construction. He shall also be responsible in specifying the materials to be incorporated in the works.

CQA Consultant
The CQA Consultant is an independent party not affiliated with the contractors, subcontractors, suppliers or manufacturers. The CQA Consultant may be the Design Engineer. The CQA Consultant has the overall responsibility for managing, coordinating and implementing the CQA activities and confirming that the contractor’s construction quality control activities are performed in accordance with the CQA Plan, construction drawings and technical specifications. The critical activities related to the construction, manufacture and installation water pipes, water pumps and

Previous Page: DCOM_Volume_III_Appendix_4 << >> Next Page: DCOM_Volume_III_Appendix_6