Appendix N: Specifications

From Ministry of Water DCOM Manual
Revision as of 11:25, 14 July 2022 by Juma (talk | contribs) (Created page with "= STANDARD SPECIFICATION FOR CIVIL WORKS= 1 GENERAL REQUIREMENTS 1.1 Permissions being obtained by the Employer The Site of the Permanent Works is shown on the drawings acc...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

STANDARD SPECIFICATION FOR CIVIL WORKS

1 GENERAL REQUIREMENTS 1.1 Permissions being obtained by the Employer

The Site of the Permanent Works is shown on the drawings accompanying these Employer’s Requirements. The Employer shall have obtained (or shall obtain) the planning, zoning or similar permission for the Permanent Works. 1.2 Plan of operations and temporary works

The Contractor shall in accordance with the Conditions of Contract, and before commencing on site, submit to the Engineer a fully detailed programme showing the order of procedure and methods by which he proposes to carry out the construction and completion of the Works, and particulars of the organisation and staff proposed to direct and administer the performance of the Contract.

The Works shall be carried forward to completion with the greatest possible expedition, to the satisfaction of the Engineer, in accordance with the programme. The information to be supplied to the Engineer shall include drawings showing the general arrangement of the temporary offices, camps, storage sheds, buildings and access roads, and details of Contractor’s Equipment and Temporary Works proposed.