A suitable site for a good reservoir shall depend upon the following factors:
 
A suitable site for a good reservoir shall depend upon the following factors:
  
a) Geological condition of the catchment area should be such that percolation losses are minimum and favors only maximum runoff<br>
+
a) Geological condition of the catchment area should be such that percolation losses are minimum and favors only maximum runoff.<br>
  
b) The reservoir site should be such that quantity of leakage through it should be minimum. Reservoir sites having highly permeable rocks reduce water tightness of the reservoir. Good types of rocks that may not allow passage of much water includes shale, slates, schist, gneiss's, and crystalline igneous rocks such as granite<br>
+
b) The reservoir site should be such that quantity of leakage through it should be minimum. Reservoir sites having highly permeable rocks reduce water tightness of the reservoir. Good types of rocks that may not allow passage of much water includes shale, slates, schist, gneiss's, and crystalline igneous rocks such as granite.<br>
 
   
 
   
c) The dam should be founded on sound, water tight rock base, and percolation below the dam should be minimum. The cost of the dam is often a controlling factor in selection of the dam site<br>
+
c) The dam should be founded on sound, water tight rock base, and percolation below the dam should be minimum. The cost of the dam is often a controlling factor in selection of the dam site.<br>
  
d) The reservoir basin should have a narrow opening in the valley so that the length of the dam is less<br>
+
d) The reservoir basin should have a narrow opening in the valley so that the length of the dam is less.<br>
  
e) The cost of real estate for reservoir including road,  rail road, dwelling relocation, etc must be as little as possible,<br>
+
e) The cost of real estate for reservoir including road,  rail road, dwelling relocation, etc must be as little as possible.<br>
  
f) The topography of the reservoir site should be such that it has adequate capacity without submerging excessive land and other properties<br>
+
f) The topography of the reservoir site should be such that it has adequate capacity without submerging excessive land and other properties.<br>
  
 
g) The site should be such that a deep reservoir is formed. A deep reservoir is preferable to a shallow one because of:
 
g) The site should be such that a deep reservoir is formed. A deep reservoir is preferable to a shallow one because of:
Line 86: Line 86:
 
* Less likely hood of weed growth.
 
* Less likely hood of weed growth.
  
h) The reservoir site should be such that it avoids or excludes water from those tributaries which carry a high percentage of silt in water<br>
+
h) The reservoir site should be such that it avoids or excludes water from those tributaries which carry a high percentage of silt in water.<br>
  
 
i) The reservoir site should be such that the water stored in it is suitable for the purpose for which the project is undertaken. The soil and rock mass at the reservoir site must not contain any objectionable soluble minerals and salts (Punmia et al., 2010).
 
i) The reservoir site should be such that the water stored in it is suitable for the purpose for which the project is undertaken. The soil and rock mass at the reservoir site must not contain any objectionable soluble minerals and salts (Punmia et al., 2010).
 +
 +
'''K.5 Empirical Methods for Capacity Evaluation of Dam Construction Sites'''<br>
 +
 +
The cross sections of the proposed dam sites are usually plotted after acquisition of data from the field by using horizontal interval and the elevations taken by GPS during reconnaissance. The plotted cross sections will show that, there is a potentiality of building a dam of a certain type and at different heights and embankment lengths. The proposed dam sites may face different challenges including a small catchment area and hence poor water yield that can fill the dam, catchment degradation due to different human activities and hence sediment transport challenges along the river valleys.etc. All these challenges have to be well addressed during design. Usually the proposed dam sites have to be refined during detailed design phase as they may be shifted on either side downstream or upstream for appropriate dam axis setting with respect to appropriate dam heights and their capacities.
 +
 +
Through site verification, a number of potential dam sites can be identified and verified with their initial capacities being empirically computed. Three empirical methods may be used to make rough estimation of the reservoir capacities and these are illustrated as methods 1, 2 and 3 as described in the next paragraphs. The appropriate dam capacities will further be appropriately determined by using contours during the detailed survey stage of undertaking the project. Materials for construction (sand, gravel and stones) of such water storage facility are to be investigated and if possible to be cheaply and locally available within the project sites with clearly noted distance from the respective sites in-line with the specifications as presented in Chapter Twelve of the Volume I of the DCOM Manual.
 +
 +
'''K.5.1 Method No.1: Queensland Water Resources Commission'''<br>
 +
 +
Capacity for each dam site is estimated basing on appropriate empirical formula to get initial guess of the expected potential storage volume for each dam. The reservoir capacity is worked out based on empirical formula estimation as per the Queensland Water Resources Commission method (cited by Nkuba, 2009). The Commission developed a method which involves determining the shape of the gully/valley slice across section and then selecting a corresponding shape from a list each of which has its own co-efficient between 0.5 and 1.6 as illustrated in Figure K.1.

Revision as of 19:28, 28 April 2020

APPENDIX K: Design of Dams for Water Sources

K.1 Introduction

In this Appendix, the following condensed information has been provided in order to assist design engineers to design dams that are expected to provide water for domestic use, to support livestock as well as for commercial and some industrial use. However, it should be borne in mind that the major water demand will be for domestic and livestock use. Furthermore, in Tanzania, majority of the existing dams for water sources are earthfill dams and only a few are rockfill dams. Furthermore, where a water source comes from a concrete dam, the primary purpose of that dam was for hydropower generation and hence the dam design is undertaken by the respective power generation agency. The Appendix has been broken into 20 sections that include:

  • Types of Dams,
  • Dam and Reservoir Pre-Surveys and Detailed Studies,
  • Reconnaissance of Potential Dam Sites,
  • Empirical Methods for Capacity Evaluation of Dam Construction Sites,
  • Preliminary Data Collection (Pre-design),
  • Designs of Earth-fill Dams,
  • Height of the Dam,
  • Design of the Embankment Filter
  • Check of the Rip-rap Adequacy for the Safety of the Structure,
  • Seepage and Stability Analysis of the Earth-fill Dams,
  • Sediment Yield in the Catchment,
  • Estimation of Evaporation from the Reservoir,
  • Different Types of Spillways,
  • Free board (Fb) Estimation,
  • Estimation of Freeboard due to wave action (fwave),
  • Embankment Crest Width (W),
  • Embankment Slopes,
  • Design Requirements for Tailings Storage Facility (TSF)
  • Dam Break/Failure Analysis,
  • Design Drawings.

K.2 Types of Dams

The general choice of a dam will depend to a large extent on the site selected for it. There are mainly three general types of dams that include:

  • Earthfill dams which also includes rockfill dams;
  • Concrete and Masonry dams;
  • Sub-surface dams.

In the case of earthfill dams, the pressure exerted by their weight spreads over a much greater area by virtue of having flatter embankment slopes. A rockfill dam consists of an embankment made of stones of irregular sizes and shape faced either with concrete or masonry earth and clay. Concrete dams require foundations of much greater bearing pressure (strength) than those on which the earthfill dams can be successfully constructed. A slight settlement in the foundation of a concrete or masonry dam may give rise to fractures whereas the same can often be well accommodated in the earthfill dams. Technically, concrete dams are rigid structures while earthfill and rockfill dams are deformable structures. Because concrete dams are not common in water supply projects in Tanzania, no further discussion of these type of dams is presented in the manual.

Sub-surface dams are usually constructed by excavating a trench within the sand-bed of a river during the dry season which is then filled with impervious material that may or may not be zoned. A further design specifications of dams for water sources is focused on earthfill dams. Rock-fill and earth-fill dams are usually built in relatively broad valley sites because large-sized machines can be operated efficiently in such sites. Selection of the dam type should be carefully made, firstly basing this on materials procurable at the dam site or in the neighbourhood, and secondly in case of fill type and where this can be found. Rain and temperature greatly affects the work period available.

A flood spillway is an indispensable part of any dam structure and therefore its size, type and the natural conditions involved in its layout often proves to be a governing factor in selection of dam type. Because of the cost of spillways and the high sediment load in main watercourses, designers should always look at the possibility of off-channel storage sites on tributaries as these can often prove to be the more cost effective alternative, even though they often involve pumped storage.

K.3 Dam and Reservoir Pre-Surveys and Detailed Studies

Pre-surveys are required to be undertaken for each of the factors listed below. Subsequent to the pre-surveys, detailed studies have to be conducted on each of the following aspects:

a) Precipitation and reservoir evaporation

b) Inflow of sediments from main and any of the tributary rivers

c) Planned highest water levels

d) Watershed surroundings

e) Water quality

f) Topographical data

g) Geology of the area

h) Foundation characteristics

i) Preliminary location and hydraulic analysis of the spillways

j) Water demand and use conditions

k) Choice of the most suitable dam site.

K.4 Reconnaissance of Potential Dam Sites

A suitable site for a good reservoir shall depend upon the following factors:

a) Geological condition of the catchment area should be such that percolation losses are minimum and favors only maximum runoff.

b) The reservoir site should be such that quantity of leakage through it should be minimum. Reservoir sites having highly permeable rocks reduce water tightness of the reservoir. Good types of rocks that may not allow passage of much water includes shale, slates, schist, gneiss's, and crystalline igneous rocks such as granite.

c) The dam should be founded on sound, water tight rock base, and percolation below the dam should be minimum. The cost of the dam is often a controlling factor in selection of the dam site.

d) The reservoir basin should have a narrow opening in the valley so that the length of the dam is less.

e) The cost of real estate for reservoir including road, rail road, dwelling relocation, etc must be as little as possible.

f) The topography of the reservoir site should be such that it has adequate capacity without submerging excessive land and other properties.

g) The site should be such that a deep reservoir is formed. A deep reservoir is preferable to a shallow one because of:

  • Lower cost of land submerged per unit of capacity,
  • Less evaporation losses because of reduction in the water spread area,
  • Less likely hood of weed growth.

h) The reservoir site should be such that it avoids or excludes water from those tributaries which carry a high percentage of silt in water.

i) The reservoir site should be such that the water stored in it is suitable for the purpose for which the project is undertaken. The soil and rock mass at the reservoir site must not contain any objectionable soluble minerals and salts (Punmia et al., 2010).

K.5 Empirical Methods for Capacity Evaluation of Dam Construction Sites

The cross sections of the proposed dam sites are usually plotted after acquisition of data from the field by using horizontal interval and the elevations taken by GPS during reconnaissance. The plotted cross sections will show that, there is a potentiality of building a dam of a certain type and at different heights and embankment lengths. The proposed dam sites may face different challenges including a small catchment area and hence poor water yield that can fill the dam, catchment degradation due to different human activities and hence sediment transport challenges along the river valleys.etc. All these challenges have to be well addressed during design. Usually the proposed dam sites have to be refined during detailed design phase as they may be shifted on either side downstream or upstream for appropriate dam axis setting with respect to appropriate dam heights and their capacities.

Through site verification, a number of potential dam sites can be identified and verified with their initial capacities being empirically computed. Three empirical methods may be used to make rough estimation of the reservoir capacities and these are illustrated as methods 1, 2 and 3 as described in the next paragraphs. The appropriate dam capacities will further be appropriately determined by using contours during the detailed survey stage of undertaking the project. Materials for construction (sand, gravel and stones) of such water storage facility are to be investigated and if possible to be cheaply and locally available within the project sites with clearly noted distance from the respective sites in-line with the specifications as presented in Chapter Twelve of the Volume I of the DCOM Manual.

K.5.1 Method No.1: Queensland Water Resources Commission

Capacity for each dam site is estimated basing on appropriate empirical formula to get initial guess of the expected potential storage volume for each dam. The reservoir capacity is worked out based on empirical formula estimation as per the Queensland Water Resources Commission method (cited by Nkuba, 2009). The Commission developed a method which involves determining the shape of the gully/valley slice across section and then selecting a corresponding shape from a list each of which has its own co-efficient between 0.5 and 1.6 as illustrated in Figure K.1.